The price is still maybe 40 percent higher than the original estimate but
it’s also 14 percent lower than the original bid.
Last week, at the Chesterton Stormwater Management Board’s meeting, Town
Engineer Mark O’Dell reported that, by tweaking the specs for the Val’s lift
station project, he and contractor Woodruff & Sons have managed to reduce
the low-bid contract price of $205,888 to around $178,000.
Among the modifications, O’Dell said: only one pump will actually be
installed in the lift station, while a backup pump will be available for use
but kept in the shop; sand bedding will be used instead of stone; and
something like $4,000 in components have been eliminated from the specs.
Even so, $178,000 is a lot more than the $125,000 to $140,000 estimate of
the project’s cost.
The idea behind the lift station is to pump stormwater from the alley behind
Val’s Famous Pizza & Grinders, located at Broadway and 11th Street. In heavy
rains that alley—the lowest point in the Town of Chesterton—tends to flood.
The lift station will pump the runoff from the alley to a large stormwater
sewer line on Lincoln Ave., about 1,100 feet to the south.
Woodruff & Sons will break ground on the project in the second or third week
of January, O’Dell told the board, and begin immediately installing the
pipe. But the contractor probably won’t take delivery of the lift-station
components themselves for six to eight weeks. Best bet: the job wll take
three to four months.
The project is being funded with the proceeds of the $880,000 stormwater
bond issued late last year. Projects already completed as part of the bond
issue: the cleaning of the Lincoln Ave. detention basin, located off 23rd
Street by the Prairie Duneland Trail; and two repairs of stormwater lines
along 23rd Street, one of them an emergency job.
Write-offs
In other business, members voted 3-0 to write off eight uncollectable
accounts totaling $50.08.
Outreach
Meanwhile, MS4 Operator Jennifer Gadzala reported that, on Nov. 28-29, she
presented a program to 240 environmental science students at Chesterton High
School on wastewater and stormwater quality.
With Thanks
MS4 Operator Jennifer Gadzala took a moment at the meeting to thank staff
for their great work over the last year. “Thanks to all department heads who
have worked with me in my MS4 capacity,” she said, “being my eyes and years
in the field and keeping on top of good housekeeping.”
November in
Review
In November the
Stormwater Utility ran a surplus of $21,849 and in the year-to-date is
running a surplus of $48,439.