Chesterton Tribune

 

 

Val's lift station comes in well under contract price

Back To Front Page

By KEVIN NEVERS

Turns out, the final cost of the Val’s Pizza lift station was quite a bit less than the bid price, and not hugely higher than the original estimate.

At its meeting Monday night, the Stormwater Management Board voted 3-0 to approve Change Order No. 2 for the project, which decreased the bid price of $205,888 by $57,193 or fully 28 percent. Change Order No. 1 had already deducted $1,130 from the bid price, bringing the final cost of the lift station to $147,565.

The original estimate had been in the neighborhood of $125,000.

The lift station--located in the flood-prone alley behind Val’s Famous Pizza & Grinders at Broadway and 11th Street, the lowest point in town--is now on line and in heavy rains will pump stormwater from the alley to a line on Lincoln Ave.

The general contractor for the project, Woodruff & Sons, worked with Town Engineer Mark O’Dell to shave the $205,888 bid price to a more manageable amount.

Under the same 3-0 vote, members also approved Change Order No. 1 for a different project, the installation of upsized concrete culverts in the Morningside subdivision. That change order increased the contract price of $107,000 by $8,149.25 or 8 percent.

O’Dell told the board that general contractor G.E. Marshall Inc. had run into a number of unexpected utility lines, including a water line which Indiana-American Water Company had failed to locate for crews.

11th Street Lift Station

In other business, members voted 3-0 to put a second stormwater lift station project out to bid, this one to drain a flood-prone alley in the area of 11th Street and West Porter Ave.

Lawson-Fisher Associates engineered the specs for the lift station at a contract price of $10,985.

Bids will be opened at the board’s next meeting, Nov. 18.

This lift station--like its sister lift station in the alley behind Val’s--will be paid for with funds from an $880,000 stormwater bond issued late in 2011.

2014 Budget

Meanwhile, the board voted 3-0 to approve the Stormwater Utility’s 2014 budget.

That budget is projecting total revenues of $438,000, almost entirely from the stormwater user fee assessed on the bimonthly sanitary sewer bills; total expenses of $424,100; and a year’s end surplus of $1,900.

Expenses include $225,000 for wages; $113,800 for pensions and benefits; $25,000 for MS4 public education; and $21,000 for material and supplies, among other things.

Kudos for Urschel Contractor

MS4 Operator Jennifer Gadzala took a moment to praise Tonn & Blank, the general contractor for the new Urschel Laboratories Inc. manufacturing facility and corporate headquarters at Coffee Creek Center, for getting out in front of MS4 construction site regulations.

Even before a foundation was poured for the building, Gadzala said, Tonn & Blank final-graded and hydroseeded the large detention pond on site. Both EPA and IDEM “encourage the stabilization of soils once major disturbance work has ceased,” she noted.

Tonn & Blank, Gadzala added, “is leading by example.”

“Thank you, Tonn & Blank and Urschel, for forward thinking and forward acting in taking care of the land out there,” President Thomas Kopko said.

September in Review

The Stormwater Utility ran a surplus in September of $6,957 and in the year-to-date is running a surplus of $12,237.

 

Posted 10/22/2013