General contractor Rieth-Riley is still shooting for a June 4 completion day
for the Downtown utility project, now in its third and final phase: the
actual replacement of the sanitary sewer main between West Indiana Ave. and
the Norfolk Southern grade-crossing.
But as Chesterton Town Engineer noted at Monday night’s meeting of the
Utility Service Board, there have been some rain days and it’s conceivable
that work will go beyond June 4.
Progress to date has “been slow but steady,” O’Dell said. On Tuesday a
second crew joined the first at the site, partly to make up for lost time.
Positions Filled
In other business, Superintendent Rob Lovell reported that all open
positions have been filled, with a start day of May 9.
Collections
Moving
Lovell also reported that the collections crew is now moving its
headquarters from a rented building to the Street Department’s old home at
609 Grant Ave., now that the Street Department has moved into its new digs
at the 15th Street facility.
April in Review
In April Chesterton used 53.26 percent of its 3,710,000 gallon per day (gpd)
allotment of the wastewater treatment plant; Porter, 77.81 percent of its
809,000 gpd allotment; the Indian Boundary Conservancy District, 91.74
percent of its 81,000 gpd allotment; and the plant as a whole, 57.24 percent
of its capacity.
In an extremely wet month—with 5.59 inches of rain—there were no bypasses in
April
And last month the Utility ran a deficit of $196,127 and in the year-to-date
is running a deficit of $73,225.