There’s no real way to sugar-coat it.
The long-discussed, long-delayed Downtown sewer replacement and separation
project, slated for the spring, is going to be a major headache and
inconvenience for Chesterton businesses and motorists.
As Interim Superintendent Mark O’Dell told the Utility Service Board at its
meeting Monday night, the project is likely to take two to three months,
although it is intended to be completed by Memorial Day in time for the
summer tourist season.
O’Dell emphasized that every effort will be made to minimize the impact on
trade and traffic in the Downtown as well as to keep businesses appraised of
the work schedule and progress. To that end the project will be tackled in
phases: South Calumet Road from Broadway to the Norfolk Southern railroad
crossing; South Calumet from Broadway to West Indiana Ave.; and South
Calumet from West Morgan Ave. and West Porter Ave.
Even so, the second phase will require the complete closure of South Calumet
from Broadway to West Indiana, O’Dell said, while it’s possible that the
first phase will require the complete closure of the at-grade Norfolk
Southern crossing.
It’s also possible, on the other hand, that by banning on-street parking
along South Cal from Broadway to the tracks enough room could be made to
allow at least one lane of traffic—either southbound or northbound—to remain
open at the crossing, O’Dell noted.
“There will be public meetings on the project,” O’Dell added. “We’ll try to
explain the scope and impact of the project to businesses and residents.”
At an estimated cost of $720,000, the project is by far the biggest ticket
item among numerous big ticket items being funded by this year’s issuance of
$5.1 million in sewer revenue bonds, an issuance itself made possible by the
14-percent increase on Jan. 1, 2009, of the sanitary sewer rate. Under that
rate hike, the average residential customer paying a bimonthly bill of $66
in 2008 is now paying a bimonthly bill of $77.25.
Members did vote 4-0 on Monday to award an engineering contract for the
Downtown project, in the amount of $67,543 to Lawson-Fisher Associates of
South Bend. Member Scot McCord was not in attendance.
The bond issue will finance a list of approximately 30 collections systems
projects, with an estimated cost of $4,348,000 and 15 plants projects, with
an estimated cost of $760,360, for a total cost of $5,108,960. An update on
some of the other projects:
•Two portable generators purchased for $50,000 are expected to be delivered
on Jan. 15.
•O’Dell is currently working with contracted consultant DLZ of South Bend on
the specs for a pair of additional generators, on-site emergency models to
be installed at two of the largest lift stations in town: Porter Cove and
KAT. The total estimated cost of the pair: $205,000.
•Gasvoda has provided a quote for the installation of new pump mounts and
guide rails in the last four lift stations in town requiring confined-space
entry to remove the pumps for service.
•O’Dell added that he is trying to arrange a trip to the Noblesville
wastewater treatment plant to inspect a kind of blower being considered for
the Chesterton plant.
Kudos
In other business, members took receipt of a letter of praise from a family
in the 700 block of South 14th Street thankful for the dedication of O’Dell
and field crew members Scot McCord Jr., Jay Iler, and Jerry Graves, after
they discovered that a contractor whom they had hired to fix a sewer problem
was “less than honest.”
O’Dell et al. arrived at the family’s home with a new contractor, Gene
Carney, who duly “cleaned up the mess left by the initial company,” while
the field crew provided a jetter and camera.
“Without the caring and dedication we observed from the Utility Department
employees, we don’t know what we would have done,” the family wrote in its
letter. “Even with the very unfortunate situation we had, having the support
of the town made a major difference. We are blessed to live in such a
wonderful town.”
Then, Porter Public Works Director Brenda Brueckheimer personally thanked
the field crew for coming to her town’s assistance during a torrential rain
earlier this fall, when a major I&I problem was discovered in a drainage
ditch on Wood Street. “I can’t tell you how much we appreciated that,” she
said. “You guys have just been wonderful.”
Finally, members praised employees Graves, Clint Iler, and Jonathan Styers
for successfully completing a centrifugal pump hydraulic seminar.
“You’re not only a credit to yourselves and the Utility,” Member Andy Michel
said of the Utility’s workforce, “you’re also a credit to the town. We hear
a lot of good stuff about you guys.”
November in
Review
In November Chesterton used 46.65 percent of its 3,752,000 gallon per day (gpd)
allotment of the wastewater treatment plant; Porter, 53.04 percent of its
767,000 gpd allotment; the Indiana Boundary Conservancy District, 74.64
percent of its 81,000 gpd allotment; and the plant as a whole, 48 percent of
its capacity. In the third driest month of the year, with only 1.41 inches
of rain, no bypasses were recorded. In November the Utility ran a surplus of
$254,608 and in the year-to-date is running a deficit of $76,662.
Year in Review
President Larry Brandt took a moment at the end of the meeting to consider
the year past. “2009 was another exciting year,” he said. “We had record
rains. A tornado too. The rate issue enabled us to put together a package of
bond projects and we’re well on the road to getting some major projects
done.”
“I can’t remember ever being closer with the Town of Porter,” Brandt added.
“It’s been good working with (Brueckheimer).”
“Once again we’re working to replace the Superintendent,” Brandt observed.
“It’s been a difficult, challenging process. Thanks to (O’Dell) for doing an
outstanding job filling in in the interim and to the employees for never
missing a beat.”
“It’s also nice to have a consistent board,” Brandt said. “We’re of the same
mind on pretty much everything.”
“2010 is going to be a fun year,” Brandt predicted.