Effective June 21
the South Shore commuter line will revert to its April 2, 2016 published
timetable next week, following completion of the universal crossover
installation project.
The South Shore
expects to complete its universal crossover installation project on June 20,
2016. Therefore, NICTD will revert to the April 2, 2016 (green and orange)
train schedule beginning Tuesday, June 21, 2016.
This notice affects
Eastbound Trains 203 and 205, and Westbound Trains 220 and 20. No other
train times are affected by this notice.
NICTD plans to
replace the May 2 paper timetable and poster with the April 2 version at all
stations. Please note that the Hegewisch ticket office will remain closed at